Our Approach

 

Home
About NH&A
Services
R.A.M.P.
Our People
Our Approach
Links
Contact Us

 

 


NH&A would approach any start to finish project using the same basic plan. Our method is easily broken down into four phases.

 

A.  DISCOVERY

  1. Investigate the existing jobsite conditions, noting building logistics.

  2. Remove adequate core samples from the roof areas involved, determining the existing composition of the roof assembly, including the possible existence of asbestos containing materials.

  3. Obtain digital photographs of all problem areas, penetrations, walls and perimeters, to be used as an aid in determining cause and affect of current conditions.

  4. Accurately measure the area involved, noting details at walls, perimeters and penetrations, loading the information to AutoCad for ready reference.

  5. Determine design load for roof structure.

  6. Research available records to determine if any manufacturer and/or contractor warranties are in effect.

B.  DISCUSSION

  1. Meet with the building owner to discuss the best possible approach to resolve the problems discovered, taking into consideration such things as budget parameters, life expectancy of the facility, project location (high wind area, fumes unacceptable, limited staging area, etc.).

  2. During the discussion phase, it might be determined that total removal and replacement is not necessary, creating the need for additional discovery in the form of a non-destructive Infrared Survey to locate any possible trapped moisture (See Services Page).

 

C.  DESIGN

  1. Based on the evidence discovered in the first stage, and through close communication with the owner in the discussion stage, the design process would begin.

  2. Selected system would be designed around applicable code authority regulations, UL and FM requirements (fire, hail, uplift), load limitations and "R" values necessary to address energy requirements.

  3. Bid documents are then prepared, outlining in detail the exact installation process for the entire assembly, including drawings of all flashing details, and any other items necessary to complete the proper application of the specified system.

D.  CONSTRUCTION ADMINISTRATION

  1. With final approval of the completed design package by the owner, the project is then entered into the bid process by following legal guidelines for the particular work involved.

  2. A pre-bid conference is conducted with interested bidders, allowing any questions regarding the project to be completely clarified.

  3. Bids are received, tabulated and, at the direction of the owner, the project is awarded.

  4. Contractor submittals for the designed work are received, reviewed and either approved or returned for revision. This process continues until all submittals are acceptable to the specifier.

  5. A pre-job conference is then held with the successful bidder, cleaning up any other detail that might have arisen, including contractor job staging, coordination of work crews with the facility director and other items related to the professional completion of the work.

  6. Full time inspection, or regularly scheduled jobsite visits by qualified NH&A personnel, depending upon the contract commitment, followed up with written reports for file is provided to assure the project specifications are followed.

  7. All interim contractor pay requests are reviewed for worthiness before being forwarded to the owner for payment.

  8. A final inspection of the work is undertaken, with an appropriate punch list of deficient items being duly noted for correction by responsible parties.

  9. All manufacturer and contractor warranties are received for the owner.

 

 

 

 

 

 

Home | About NH&A | Services | R.A.M.P. | Our People | Our Approach | Links | Contact Us

This site was last updated 02/22/03